SHREE POWER PLANT Shree Cement Limited have installed 120 MW captive power plants split at two locations (Beawar & Ras) to meet out complete power needs of 10 million tonne Integrated Cement Plant. Captive Power Plants are running in parallel with State grid and exporting power to our cement grinding unit located at Khushkhera, around 300 KM away from Beawar, by utilizing the facility of Open Access with complex monitoring and control to optimize cost of power.
- Commissioned 2x18 MW Greenfield Power Plant at Beawar in 2002 and running successfully. One 6 MW TG is also operating successfully with excess steam available from this 2x18 MW Power Plant.
- In addition to above 2x18 MW Greenfield Power Plant has been commissioned and is operating successfully at our new Ras Cement Plant. Construction of balance 2x18 MW is in progress and likely to be commissioned in April and October in this year.
- We have also installed a Waste Heat Recovery Plant of 3 MW with new design concept for 1st cement kiln. This plant has been commissioned in March, 2008.
- We have received “Water Efficient Unit Award" at the National Award for Excellence in Water Management 2007 conducted by CII – Godrej GBC on 29 & 30 November 2007 at CII-Sohrabji Godrej Green Business Centre, Hyderabad.
Addition 6 MW capacity enhancement is in progress. |